Early Works Set to Begin for New Uxbridge Scugog Animal Shelter

The Townships of Uxbridge and Scugog are pleased to provide a project update as the new Animal Shelter moves into its next phase. Following a previous announcement, both Councils have now approved a report that outlines the construction strategy and authorizes the start of critical early-site work.

With the building permit secured, the Townships are moving forward with essential preliminary site works. This includes site access (driveway cut-in), excavation, well and foundation installation and hydro utility coordination.

The project will proceed using a trade-by-trade procurement model, rather than engaging a single general contractor. This approach is expected to improve cost transparency, optimize scheduling, and create opportunities for potential savings.

A $170,000 preliminary budget allowance has been approved to support this early phase. These works will ready the site for above-grade construction before winter and include installation of footings and frost walls, subgrade preparation, in-floor plumbing readiness, and setup of a temporary construction trailer. Hydro rough-in is also included at this stage.

The project will now transition into preliminary site work, followed by completion of trade pricing, final budget approval, and then full construction commencement. Substantial completion will follow in line with project timelines as outlined in theĀ full report.

The Townships remain committed to building a modern, efficient animal shelter that meets the needs of both communities, staff and animals. Additional updates will be provided as work progresses on site.